Short-term Effective Value Changes
:
We can divide the short continuous
change of the voltage-active value
into three parts; These times are
related to the processing times of
the protective circuitry. The
defined time and amplitude values of
the short term changes according to
IEEE 1159: 2009 are shown in Figure
1.
Figure 1. Short-term changes
according to IEEE 1159: 2009
Short-term voltage variations; The
starting and removal of the loads
with high take-off currents are due
to reasons such as disconnection in
the power distribution system, short
circuits. These changes are seen as
swells, voltage pitting or voltage
cuts according to the system
condition and where the error
occurred. The changes in time and
amplitude current can also be
classified as short-term
disturbances.
If the supply voltage or the load
current does not exceed 1 minute,
the effective value is less than 0.1
pu. Power systems errors and
hardware
defects can be the cause of
downtime. The interruption is
measured by the time the voltage
amplitude is continuously below 10%.
It is usually seen after tension
pitting. Interruption of the
protective devices may occur
immediately after the voltage
pitting in the transmission line.
The duration of the interruption is
dependent on the reclosing
performance of the protective
device. The
decrease of the effective value of
the voltage between 0.1 pu and 0.9
pu within a period of one
half-period to 1 minute is called
sags. The definition of voltage
pitting is not considered to be the
level of pitting, but the residual
voltage level. For example, voltage
pitting of 80% means that the
effective value of the voltage is
0.8 pu based on the rated operating
voltage. Tension pitting may be
caused by failures in the system as
a result of high-current loads. An
induction motor draws 6 to 10 times
more than the nominal current at the
time of take-off. Due to the system
impedance, these high currents cause
the voltage level to pit. In
general, the period is defined as
half a period to 1 minute. Since the
change in rms value is not high in
the tension pitting of short
duration from the half-period,
short-term pitting is classified as
temporary.
It is called swells when the
effective value of the voltage is
over 1.1 pu in a period of 1 minute.
The resulting voltage is indicated
by the amplitude and its value is
always greater than 1 pu. The
tension is not as frequent as
pitting. It is caused by
malfunctions in transmission or
distribution systems, as in the case
of voltage pitting. It is usually
seen in healthy phases during single
phase-earth fault. However, it can
also occur during the
decommissioning of large loads and
energization of large capacitor
groups. The
intensity of the voltage rise varies
depending on the condition of the
fault, the system impedance and the
ground. During a single
phase-to-earth fault in a groundless
system, the phase-to-earth voltage
in the healthy phase rises to 1.73
pu. No voltage rise will occur as
you approach an effectively earthed
station. Because the distribution
center transformer is usually
connected to the triangle-asterisk
(ı ı Y) and has zero impedance zero
sequence for the fault current.
|